If the cost variance is positive and the schedule variance is also positive, then it indicates that …
a) Project is under budget and behind schedule
b) Project is over budget and behind schedule
c) Project is under budget and ahead of schedule
d) Project is over budget and ahead of schedule

The answer is C because EV-AC>0 and EV-PV>0, both positive signals.
 

Talk to us...

Get information or have a Partner contact you. Call us on (206) 355-2744 or...Email us...

Industries

Manufacturing
Distribution
Transportation
Energy
Retail
Software/Internet
Telecommunications
Non-profit
Biotechnology
Healthcare
Insurance
Government

Strategy and Execution

  • Business Performance Management
  • Process Improvement
  • Project Turnaround
  • Program Management & PMO Setup
  • Merger & Acquisition Integration
  • Product Innovation
  • Product Management
  • Strategy Alignment & Execution

Technology Management

  • IT Architecture
  • IT Infrastructure
  • Operations (ERP/SCM)
  • Sales & Marketing (CRM)
  • Application Development
  • Application Integration
  • Software Selection
  • Outsourcing/Offshoring Management

Solutions Management

  • Business Requirements Definition
  • Functional Requirements
  • Stakeholder Requirements
  • Quality-of-service Requirements
  • Implementation Requirements
  • Traceability Matrix
  • Kaizen/Lean Six Sigma
  • Change Management